Project Health
Executive overview of readiness, risk, and delivery status
Pilot Project Context
This dashboard represents the WW Pilot - Stage 1 Expansion project for City Water Authority.
Project health executive metrics and charts
Systems ready for handover
12
Binder-ready systems
Asset completeness
87%
Required documentation coverage
Submittals pending
23
Awaiting review or resubmission
Open deviations
8
Active non-conformances
Commissioning complete
72%
Program-wide progress
Inspection pass rate
94%
Recent inspection outcomes
Asset completion trend
Program completion percentage by month (demo pilot data)
Tracked assets
Completion volume (filtered view)
Completed
1085
Total
1247
Commissioning progress by system
Readiness by major system (percent complete)
Documentation completeness
Asset count with complete records per category
Handover binder status
Distribution across readiness states
Submittal pipeline
Volume by submittal status
Open deviations by severity
Issue concentration (non-conformance register)
Open risks by severity
Active risk register concentration
Inspection pass rate trend
Weekly pass rate trajectory (demo data)
Open risks register
Active risks from the pilot register (same data as charts above).
Open Risks
| ID | Description | Severity | Status |
|---|---|---|---|
| RISK-001 | Delayed delivery of critical pump components for P-101 | High | Open |
| RISK-002 | Incomplete as-built drawings for Electrical Distribution system (CP-401) | Medium | Open |
| RISK-003 | Pending approval for Chemical Feed system modifications (CFP-205) | Medium | Open |
| RISK-004 | Missing test certificates for Filtration system (FV-301) | Low | Open |