Handover Dashboard
Overview of handover readiness and package tracking metrics
Total Handover Packages
24 Packages
Export jobs (asset + facility handover binders)
Completed Packages
0 Packages
Completed handover compilations
Running Packages
0 Packages
Compilations in progress
Failed Packages
0 Packages
Failed export jobs
Systems (100% complete)
18 Systems
Systems where all assets are complete
Incomplete assets
6 Assets
Assets not yet complete (by system)
Binder Completeness
87 %
Completed handover packages % of total
Asset completion by system
Average Readiness
87%
Most Ready
95%
Pumping Systems
✓●Pumping Systems
95%95%
●Chemical Feed
92%92%
Filtration
89%89%
Electrical Distribution
85%85%
Instrumentation & Control
82%82%
HVAC
78%78%
Deliverable Coverage
96%
Overall Coverage (5504 / 5718)
●Maintenance Manuals
1130 / 115698%
●Test Certificates
1066 / 109298%
●Warranty Documents
1008 / 103497%
●Operation Manuals
1142 / 118996%
●As-Built Drawings
1158 / 124793%
Incomplete assets by system
Total incomplete
192
Highest Gap
89
Pumping Systems
⚠Pumping Systems
8989
Electrical Distribution
4747
Chemical Feed
2626
Filtration
1818
Instrumentation & Control
1212
Handover exports completed (trend)
87
Exports this period (Aug)↑
Handover Package Tracker
| ID | Description | System | Package Type | Severity | Triggered By | Status | Date |
|---|---|---|---|---|---|---|---|
| HP-001 | Pumping Systems handover package incomplete - missing O&M manuals for P-101 | Pumping Systems | System Turnover | High | Handover Team A | Open | 2026-03-15 |
| HP-002 | Electrical Distribution binder pending final acceptance signatures (CP-401) | Electrical Distribution | Binder Package | Medium | Handover Team B | In Progress | 2026-03-18 |
| HP-003 | Chemical Feed system turnover blocked by pending NCR closure (NCR-003) | Chemical Feed | System Turnover | High | Handover Team A | Open | 2026-03-16 |
| HP-004 | Filtration system missing final test certificates (FV-301) | Filtration | System Turnover | Medium | Handover Team C | Open | 2026-03-20 |
Turnover & Handover Workflow
Track system-level turnover packages, staging, and readiness blockers
Export Packs & Handover Binders
Browse export packages and handover binder contents by system