Maintenance Log
Inventory-linked maintenance and support activities for plant assets
Total Activities
3
Scheduled
1
Completed
2
Open Work
1
| Activity | Facility / System | Asset Tag | Item / Linked Code | Status | Scheduled | Completed | Performed By |
|---|---|---|---|---|---|---|---|
Quarterly mechanical seal inspection and lubrication Preventative | Main Treatment Plant Pumping Systems | P-101 | - | Completed | 3/5/2026 | 3/5/2026 | Mike Technician |
Annual flow transmitter calibration verification Calibration | Main Treatment Plant Instrumentation & Control | FT-501 | - | Scheduled | 3/20/2026 | - | Instrument Tech A |